Key facts
Location: Birling Road, Leybourne Chase
Work: Installing 20 metres of water main
Started: Monday 11 August
Duration: Approx. three weeks
Investment: £115,000
Work has begun on installing around 20 metres of new water main in Birling Road, Leybourne Chase. By laying this new main we’ll be able to provide the community with higher quality drinking water.
How long will this project take?
This project started on Monday 11 August, and is expect to take around three weeks to complete. Our team will work quickly to complete the project sooner, if possible.
Will the road be closed?
This work will require us to close Birling Road, between the junctions of Bannister Way and Bull Road. We’ll work in phases along the road to minimise disruption and access will be maintained for residents.
The diversion route, pictured here, will take motorists through Leybourne Chase, down to the A20 and on to the A228.

Project Timeline
Thursday, 4 September 2025
15:38 PM
Project update
We’re very sorry to our customers in the West Malling area that have been inconvenienced by this road closure.
Unfortunately, due to some unexpected complications, we need to extend the duration of this project by around two weeks.
We will aim to get the remaining work done as quickly and efficiently as possible.
Monday, 11 August 2025
08:00 AM
Project update
Work has now begun on our project on Birling Road, West Malling.
We expect the work to take around three weeks to complete.
We will update this webpage regularly throughout the project.